Total Measured and Indicated
Resources
|
|
Project
|
Short
Tons (millions)
|
Gold
Grade (opt)
|
Contained
Gold (ounces)
|
Cut-Off
Grade (opt gold)
|
|
Golden Eagle1
|
31.4
|
0.055
|
1,744,000
|
0.020
|
|
Pan2
|
34.65
|
0.018
|
608,700
|
0.006
|
|
Total
|
66.05
|
0.036
|
2,352,700
|
|
|
|
Total Inferred Resources
|
|
Project
|
Short
Tons (millions)
|
Gold
Grade (opt)
|
Contained
Gold (ounces)
|
Cut-Off
Grade (opt gold)
|
|
Golden Eagle1
|
5.1
|
0.038
|
192,000
|
0.020
|
|
Pan2
|
1.6
|
0.017
|
26,500
|
0.006
|
|
Midway3
|
5.5
|
0.039
|
215,500
|
0.010
|
|
Spring Valley4
|
87.8
|
0.021
|
1,833,000
|
0.006
|
|
Total
|
100.0
|
0.023
|
2,267,000
|
|
1.
Golden Eagle Footnote
Effective date: July 30, 2009. Eric Chapman
(M.Sc., C.Geol) of Snowden Mining Industry Consultants Inc. is the designated
Qualified Person who has prepared the Golden Eagle resource estimate. Mineral
resources have been estimated in accordance with the standards adopted by the
Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") Council in
November 2003, as amended, and prescribed by the Canadian Securities
Administrators' National Instrument 43-101 Standards of Disclosure for Mineral
Projects. The resource estimate includes verified drill results from 222
historic holes that were available up to May 1, 2009. Verification was
completed by comparison of gold values to lab certificates and drill logs
obtained from historic operators of the project. Only gold values that had lab
certificates or drill log verification were utilized in the resource estimate.
Mineralized domains were established by interpretation of geological,
structural and assay information on sections and plans. Assays within the
domains were composited into 5 foot intervals. Search distances and directions
were established using spherical variograms on the composites within the
domains. A capping threshold of 0.10 to 0.50 ounce per ton (opt) gold was
utilized depending upon the domain, and assays greater than the capping
threshold would be set to that value. Less than 0.2% of the samples were
affected by the capping. A density factor of 13.7 cubic feet per short ton (ft
3/st)
was applied to the mineralized bedrock material, and 13.5 to 14.3 ft
3/st
was applied to surrounding bedrock. A tonnage factor of 15.1 ft
3/st
was applied to overlying glacial till. A three dimensional block model was
generated using Datamine(r), a commercially available mine planning software
package. Composited assays were used to estimate tons and gold grades within
domains using an ordinary kriging estimation methodology. Resources reported
are included within a Lerchs-Grossmann (L-G) optimization shell, which was
generated using a $750 per ounce gold price and 85% gold recovery. The L-G
shell is an economic test that simulates a break even pit using current mining
costs. Further details of the estimation procedure are available in the NI
43-101 report posted on SEDAR (
http://www.sedar.com).
2.
Pan Footnote
Effective date:
December 1, 2009. Don Harris (M.Sc., CPG) Vice President-Advanced Projects of Midway Gold Corp. is
the designated Qualified Person who has prepared the Pan resource estimate update, based upon the Pan NI 43-101 report prepared by Mine Development Associates and dated effective January 15, 2005. Mineral resources have been estimated in accordance with the standards adopted by the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") Council in November 2003, as amended, and prescribed by the Canadian Securities Administrators' National Instrument 43-101 Standards of Disclosure for Mineral Projects. The resource estimate is based on verified drill results from 864 exploration holes available up to July 1, 2009. Mineralized domains were established by interpretation of geological, structural and assay information on sections and plans. Assays within the domains were composited into 10 foot intervals. Search distances and directions were established using spherical variograms on the composites within the domains. A density factor of 13.5 cubic feet per short ton (ft
3/st) was applied to the siltstones and shales, 12.3 ft
3/st to limestones, and 15.0 ft
3/st to overlying volcanic tuffs. Historic metallurgical test work by Alta Gold Company and Castleworth Ventures Inc. shows oxide leach recoveries ranging from 75-94% in column testing. A three dimensional block model was generated using Surpac(r), a commercially available mine planning software package. Composited assays were used to estimate tons and gold grades within domains using an ordinary kriging estimation methodology. Resources reported are included within a Lerchs-Grossmann (L-G) optimization shell using an 80% crushed leach gold recovery. The L-G shell is an economic test that simulates a break-even pit using current mining costs. Further details of the estimation
procedure are available in the NI 43-101 report posted on SEDAR (
http://www.sedar.com).
3.
Midway Footnote
Effective date: February 24,
2005. Karl S. Hackett (P.Eng) of KRJA Systems Inc./Maptek is the designated
Qualified Person who has prepared the Midway resource estimate. Mineral
resources have been estimated in accordance with the standards adopted by the
Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") Council in
November 2003, as amended, and prescribed by the Canadian Securities
Administrators' National Instrument 43-101 Standards of Disclosure for Mineral
Projects. The resource estimate includes drill results from 195 holes up to
October 2004 in the Discovery, 121, and 63-77 Zones. Mineralized domains were
established by interpretation of geological, structural and assay information
on sections. Assays within the domains were composited into 10 foot intervals.
In high-grade zones, a capping threshold of 9.00 opt gold was utilized, and
assays greater than 9.00 opt gold were set to 9.00 opt gold. In low-grade
zones, a capping threshold of 0.3 opt gold was utilized, and assays greater
than 0.3 opt gold were set to 0.3 opt gold. A density of 13.0 cubic feet per
short ton (ft
3/st) was applied to material in the high and low-grade
zones, and 16.0 ft
3/st was applied to country rock. A three
dimensional block model was generated using Vulcan(r), a commercially available
mine planning software package. Composited assays were used to estimate tons
and gold grades within domains using an inverse distance cubed (ID
3)
estimation method, utilizing an 0.010 opt cut-off grade. Further details of the
estimation procedure are available in the NI 43-101 report posted on SEDAR (
http://www.sedar.com).
4.
Spring Valley Footnote
Effective date: March 25,
2009. Eric LeLacheur (M.Sc., CPG) Project Manager of MGC Resources Inc. and Don
Harris (M.Sc., CPG) Vice President-Advanced Projects of Midway Gold Corp. are
the designated Qualified Persons who have prepared the Spring Valley resource
estimate update, based upon the Spring Valley NI 43-101 report prepared by AMEC
and dated effective March 7, 2008. Mineral resources have been estimated in
accordance with the standards adopted by the Canadian Institute of Mining,
Metallurgy and Petroleum ("CIM") Council in November 2003, as amended, and
prescribed by the Canadian Securities Administrators' National Instrument
43-101 Standards of Disclosure for Mineral Projects. The resource estimate
includes drill results from 450 holes up to December 31, 2008 in the Pond,
Sill, Porphyry, Valley Breccia, North Hill, West Diatreme, and Big Leap Zones.
Mineralized domains were established by interpretation of geological,
structural and assay information on sections. Assays within the domains were
composited into 10 foot intervals. Search distances and directions were
established using spherical variograms on the composites within the domains. A
capping threshold of 1.00 opt gold was utilized, and assays greater than 1.00
opt gold were set to 1.00 opt gold. This cap is slightly lower than that used
by AMEC in 2008. Higher grade composites between 0.25 and 1.0 opt were given a
restricted range of 100 feet to limit high grade influences. A density of 12.6
cubic feet per short ton (ft
3/st) was applied to all bedrock
material, and 14.0 ft
3/st was applied to alluvium overburden. A
three dimensional block model was generated using Surpac(r), a commercially
available mine planning software package. Composited assays were used to
estimate tons and gold grades within domains using an inverse distance cubed
(ID
3) estimation method. Resources reported are included within a
Lerchs-Grossmann (L-G) optimization shell, which was generated using a $715 per
ounce gold price. The L-G shell is an economic test that simulates a break even
pit using current mining costs. Further details of the estimation procedure are
available in the 2009 Midway NI 43-101 report and the 2008 AMEC NI 43-101
report, both posted on SEDAR (
http://www.sedar.com).